For information on the requirements relating to the selection, handling, positioning, erection and removal of poles, see NS128 Pole Installation and Removal. When working on or around poles, please ensure the safety precautions outlined in NS128 Pole Installation and Removal are followed. Information about safe work practices, including safety clearances from overhead powerlines, can be found in the Safe Work Australia and SafeWork NSW Codes of Practice. |
Where an existing in-service Ausgrid pole is required to be held in place due to existing or expected instability of the pole or pole footing, only Ausgrid directed contractors or Ausgrid staff are permitted to perform this work.
Ausgrid charges for the provision of the pole holding service as per the regulated rates applicable for this service.
Depending on the type of work you are carrying out, Ausgrid has three types of responses to requests for pole holding.
Any planned excavation work which may require one or more poles to be held (based on the guideline listed in the diagram below) should be discussed with Ausgrid at least four weeks in advance of the proposed excavation date. However, transmission poles (33kV to 132kV poles with insulators at least 500mm long) will require eight weeks’ notice due to outage limitations on holding poles.
If you are advised that a pole will need to be held by Ausgrid, the following will occur:
Please email resservicesupport@ausgrid.com.au with all available information about the proposed works, in particular the details of the excavation occurring near Ausgrid’s pole(s). Please include the Ausgrid pole number(s), the address of the site and the proposed date and duration of the pole holding requirements.
This situation only applies where an uncontrollable and unpredictable event has adversely impacted another utility or other infrastructure benefitting the public.
In order to repair the impacted infrastructure, the stability of an Ausgrid pole may be adversely affected. Where these events are reported, the following will occur:
Ausgrid resources for holding poles include business critical staff and equipment which is not available for long periods. If your works are expected to be of extended duration (longer than 1 day), you may be required to undertake initial works to ‘make safe’ the impacted infrastructure until a long-term solution for supporting Ausgrid’s poles can be determined.
Please call 13 13 88 for all emergencies related to the Ausgrid network.
This situation only applies where the stability or condition of Ausgrid's asset is directly impacted as a result of an uncontrollable or unpredictable event; an example of this is if a water main has burst and the flowing water has eroded the foundations of a pole and is causing direct damage to the pole (see example in the image on the right).
However, if water from a burst water main has not damaged the pole’s foundations but the responsible water utility needs to excavate in close proximity to the pole to make an immediate repair, this would be classified as Emergency Work (as above). Ausgrid will seek full recovery of costs from the responsible party via legal processes, unless a prior agreement is in place (e.g., the utility has entered into an agreement to manage ongoing damage cases).
Where Ausgrid is called to these situations:
Please call 13 13 88 for all emergencies related to the Ausgrid network.
To check the Zone Requirements prior to excavation, please refer to the Holding Poles Zone Reference Diagram.